Managing a project to completion is a challenging endeavor. Today’s projects are complex, span multiple years, and use partnering and/or contracting structures tailored to meet unique project requirements. Effective project risk management is a critical driver of success.

Risk mitigation in project management requires the consideration of all activities and milestones in your schedule, with a strong focus on collaboration and control of project interfaces. Any unknown schedule discrepancies can put your project at risk.

 Risk Mitigation in Project Management - Uncover Schedule Discrepancies

 

Be Alert for Potential Project Risks

The contract strategy used by owners of today’s medium-to-large-scale projects results typically in multiple scope packages awarded to several contractors dispersed geographically. This strategy's objective is to minimize technical, resourcing, quality, and delivery risks to the overall project.

The Construction Industry Institute reported the average cost overrun increase for projects without formal interface management is 18%. As such, projects are being pushed to effectively manage interfaces from early planning and Front End Engineering and Design (FEED) through construction, commissioning, and handover to operations to add risk mitigation in project management and deliver business value.

While well-meaning, contracting strategies create additional project risk by forming project interfaces and dependencies between the various scopes of work and make the contractors responsible for delivery.  Managing these interfaces, the stakeholder relationships, and the interactions related to interface deliverables is the discipline of interface management.

 

What Is Interface Management?

“Interface Management is a project management and systems engineering management discipline applied to address the risk associated with project interfaces and the interactions they require – both internal to the project and between external entities influencing the project.” - Michael Bible and Susan Bivins, Project Interface Management - Reducing Risk on Major Projects

Interface management on projects starts with the identification of interface points early in the project life cycle for each scope package. Interfaces may be physical, commercial, or environmental. Examples of where interfaces exist include:

  • Environmental Impact Assessment (EIA) – Owner/operators interface with a governing body for approval to proceed with the project, requiring input from multiple sources.
  • Main Pipe Rack Corridor – Multiple scopes of work being fed utilities and/or delivering processed liquids/solids/gases with multiple engineering and construction contractors dependent upon the completion and connection to the main arterial pipe rack.
  • Packaged Unit – A key supplier’s packaged processing unit within an engineering and construction contractor’s scope of work.

Interface points can be a scope package, internal, or external (existing between different contractors and scope packages).

Interface management encourages contractors responsible for work packages to communicate and share information and deliverables amongst each other. Technical information such as pressure and flow rates, process flow diagrams, battery limit tables, the timing of construction activities, and testing times are just a small sampling of the information and documents that must be shared and exchanged between scope packages to manage project interfaces successfully. Successful risk management hinges on the coordination and timely completion of these activities and deliverables.

Interface management focuses on a specific type of project risk management. Too often, the interface information is not systematically compared to the project's schedule, resulting in missing project details in the existing schedule. As a result, projects run the real risk of interface-related schedule risk going undetected.

While it is encouraged and necessary to support these open communication channels, it is essential to keep an eye on the baseline schedule to ensure potential misalignment of deliverables, tasks, or activities are brought to the key stakeholder's attention.

 

The Importance of Integrating The Project Schedule

Integrated scheduling is a critical component of effective project risk management. Defining and publishing an integrated master schedule provides a standardized way to communicate new and existing tasks to all work package owners. Through an integrated schedule, the viewers can identify the ideal project plan and easily make necessary changes.

Project schedules will have hundreds or thousands of activities. And your interface management system will also be tracking hundreds or thousands of interfaces. It is unrealistic to try to represent all interface activities and relationships in the schedule.

With the challenge of achieving this level of integration, projects are looking at alternatives. The logical choice is integration between the project schedule and interface management. The schedule tracks the higher-level milestones and activities; while the interface management system monitors the specific deliverables between the various project participants.

Linking the interface details to the schedule milestones will bring projects an increased level of awareness and provide the transparency needed to ensure that interface-related activity aligns with the schedule.

Early visibility of potential schedule issues (e.g., out of sync dates discovered in the Work Schedule Discrepancy Report – Figure 2) is key to giving the project management team the lead time needed to mitigate the risk in the project.

 

Reach a Higher Level of Risk Mitigation in Project Management

It’s a given that projects have and will continue to grow in size and complexity. With the move away from the traditional nomination of a single EPC to joint venture consortia, project management contractors (PMCs), specialist fabricators, multiple engineering, design contractors, etc., there is an increasing number of interfaces between different stakeholders and differing contractual arrangements. The increase in collaboration drives significant importance to manage the project schedule effectively.

1. Projects have an increased need for predictability and cost containment

The result is that project teams must be highly effective, flexible, and have access to all related information to remain on top of things before they become serious issues. If projects are considering the project schedule without interface activities, they are missing significant sources of critical project information.

2. Transparency is a key factor in project execution and delivery success

The additional transparency provided by bringing together the key project management disciplines of schedule planning and interface management will further equip project managers, planners, and interface managers with additional information to identify potential schedule risk early.

A successful integration strategy ensures a project's interfaces and activities are on track and sync with your overall project schedule.

3. Effective risk mitigation in project management is a significant contributor to project success.

Poor communication, poor scope definition, and failure to clarify expectations are all significant focus areas for project risk management. Having an interface management system (IMS)  drive improved scope delineation will reduce these risk factors. Incorporating an interface management strategy will facilitate communication and ensure clarity of expectations.

Integrating the project work schedule with the IMS will provide valuable data to identify early potential risk and provide a resolution when the scope is not well understood, and interfacing parties do not understand expectations.

 

How-To Guide

For more information on how to practically implement this integration,
download our detailed step-by-step schedule integration paper.
The guide includes the content above that illustrates the benefits this integration offers as well as an in-depth breakdown of how you can implement this project risk management strategy.

If you do not have an interface management system, consider Coreworx Interface Management. It is designed to give you the control and processes to easily identify interfaces, specify responsibility, improve project coordination, and mitigate project risk. Feel free to reach out and learn how Coreworx Interface Management can help you mitigate risk in project management.